2021 Street Resurfacing |
Post- Bid |
Walls Bros. Asphalt Co. Apparent low, responsible bidder |
7/12/2021 |
9/17/2021 |
Various- See map in Description |
Streets will be closed while they are being worked on. |
2021 Resurfacing.docx |
2021 Sidewalk ADA Compliance |
Post- Bid |
Grissom Construction, LLC Apparent low, responsible bidder |
Spring 2021 |
7/2/2021 |
Various- See map in Description |
Sidewalks, tree lawns, and parking spaces will be blocked while work is being done. |
2021 ADA .docx |
Sanitary Sewer Replacement Project |
Preconstruction |
J & J Schlaegel, Inc. |
Early March |
11/30/2021 |
Alley north of Park Ave., from Washington Ave. to the east of Virginia St. Alleys between 1100 blocks Lincoln St. & Virginia St. and north of 900 block of Maple St. |
The alleys will be closed from 7:00 AM- 5:00 PM Monday thru Friday during the project. Residents will be notified before the closures. |
Sanitary Sewer.docx |
Hydraulic Canal Spillway Bridge Rehabilitation |
Post- Bid |
R.B. Jergens Contractors, Inc Apparent low, responsible bidder |
|
6/30/2021 |
Spillway 1 is located north of Ziegler Rd. |
The bike path will be closed from Ziegler Rd. to the Old Water Plant during the project |
Hydraulic Canal Spillway.docx |
Water and Main Parking Lot |
Design |
|
|
|
Northeast corner of Water and Main intersection |
|
|
E. Ash Street (US 36) Pavement Repairs |
Preconstruction |
Barrett Paving Materials, Inc. |
|
5/31/2021 |
Eastbound Ash Street (US 36) from Scott Dr to northbound I-75 |
Lane closures will occur at night during the project. Traffic will be maintained. |
E Ash Street Repaving.docx |
E. Ash Street (US 36)Traffic Study |
Pre-bid |
|
5/1/2021 |
|
E. Ash Street (US 36) from Scott Drive to Kienle Drive |
Intermittent lane closures will occur. Traffic will be maintained. |
E Ash Street Traffic.docx |